Leveling Warnings Section of the Leveling Report Log

Overview

Use this section to view the leveling warnings for various projects.

Screen Elements

Non-driving resource assignments moved off activity dates due to leveling field

A list of non-driving activity assignments where a date change occurred after the project was leveled.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, click the Actions menu and select Run Leveler... (Shift+F9).
  4. In the Level Resources dialog box, click the Options tab.
  5. On the Options tab, select the Display leveling log upon completion and click Level.
  6. In the Leveling Report Log, expand the Leveling Warnings section.

Related Topics

About Resource Leveling

Leveling Project Resources