Scheduling Results Section of the Leveling Report Log
Overview
Use this section to view the results of scheduling for the selected project. All fields are read-only.
Screen Elements
Number of Activities Scheduled field
The number of scheduled activities for the project.
Number of Relationships with other projects field
The number of relationships between the selected project and other projects.
Earliest Early Start Date field
The earliest possible date the activity can start.
When scheduling on the forward pass, if the activity has any driving resource assignments, the application calculates the early start date as the earliest Early Start date of all driving resource assignments.
Latest Early Finish Date field
The latest possible date that the activity can finish.
This date is calculated when the project is scheduled and is used to calculate total float.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, click the Actions
menu and select Run
Leveler... (Shift+F9).
- In the Level Resources dialog box, click the Options tab.
- On the Options tab, select the Display leveling log upon completion and click Level.
- In the Leveling Report Log, expand the Scheduling Results section.
Related Topics
Last Published Wednesday, July 10, 2024