Projects Checked Section of the Schedule Check Report Dialog Box
Overview
Use this section to view projects that were checked and included in the report.
Screen Elements
Project ID field
The unique identifying code for each project that the application checked. Click this link to view the project.
Project Description field
The brief description of the project. Click this link to view the project.
Data Date field
The progress point, or "as-of date", for activities in the project. Project status is up-to-date as of the data date. You can set the data date when you schedule the project or apply actuals, or you can set it manually. Set it manually if resources manually update activity progress and you do not plan to reschedule the project or apply actuals.
Total Activities field
The number of activities in the project.
Complete Activities field
The total number of activities in the project with an actual finish date.
Total Links field
The total number of links to or from activities in open projects. This number includes links that exist between activities in open projects and activities in closed projects.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.