Late Activities - Activities Scheduled to Finish Later Than the Project Baseline Section of the Schedule Check Report Dialog Box
Overview
Use this section to view activities that are scheduled to finish later than the project baseline. This indicates how well the project is performing against the currently selected baseline.
Only a subset of the activities in the open projects are checked. WBS summary activities, activities with an actual finish date, milestones, and Level of Effort activities are removed from the subset to create the list of activities checked for a Baseline Finish Variance of less than 0. The Actual percentage is calculated as the number of activities found that match the check divided by the total number of subset activities checked.
Screen Elements
Project ID field
The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.
Activity ID field
The unique identifying code for the activity which failed the check. Click this link to view the activity.
Activity Name field
The name of the listed activity. Click this link to view the activity.
Finish Variance (hours) field
The number of hours the task has been delayed.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions