Resource/Cost - Activities That Do Not Have an Expense or a Resource Assigned Section of the Schedule Check Report Dialog Box
Overview
Use this section to view activities that do not have an expense or resource assigned. Plans without resources or costs are not as meaningful particularly when you are tracking Earned Value.
Only a subset of the activities in the open projects are checked. WBS summary activities, milestones, and Level of Effort activities are removed from the subset to create the list of activities checked for no resources or expense assignments. The Actual percentage is calculated as the number of activities found that match the check divided by the total number of subset activities checked.
Note: There is no check for the number of units or the value of the expenses.
Screen Elements
Project ID field
The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.
Activity ID field
The unique identifying code for the activity which failed the check. Click this link to view the activity.
Activity Name field
The name of the listed activity. Click this link to view the activity.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions
Related Topics
Last Published Wednesday, July 10, 2024