Invalid Progress Dates - Incomplete Activities Before the Data Date Section of the Schedule Check Report Dialog Box
Overview
Use this section to view incomplete activities that are scheduled before the data date.
Only a subset of the activities in the open projects are checked. WBS summary activities, Level of Effort activities, and activities with actual finish dates before the data date are removed from the subset to create the list of activities checked for planned dates that occur before the data date. The Actual percentage is calculated as the number of activities found that match the check divided by the number of subset activities checked.
Screen Elements
Project ID field
The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.
Activity ID field
The unique identifying code for the activity which failed the check. Click this link to view the activity.
Activity Name field
The name of the listed activity. Click this link to view the activity.
Data Date field
The progress point, or "as-of date", for activities in the project. Project status is up-to-date as of the data date. You can set the data date when you schedule the project or apply actuals, or you can set it manually. Set it manually if resources manually update activity progress and you do not plan to reschedule the project or apply actuals.
Start Date field
The current start date of the activity. For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.
Finish Date field
The current finish date for the activity. For not started activities, this is the planned finish date. For in-progress activities, this is the remaining early finish date. For completed activities, this is the actual finish date.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions
Related Topics
Last Published Wednesday, July 10, 2024