Links to Closed Projects - Activities with Links to Closed Projects Section of the Schedule Check Report Dialog Box
Overview
Use this section to view data for activities that have links to closed projects.
Screen Elements
Predecessor Project ID field
The identifying code for the project containing the predecessor activity that failed the check.
Predecessor Activity ID field
The identifying code for the predecessor activity that failed the check.
Predecessor Activity Description field
The brief description of the predecessor activity.
Relationship Type field
The type of relationship between two activities.
Valid values are:
Finish to Start: The successor activity cannot start until its predecessor finishes.
Finish to Finish: The successor activity cannot finish until its predecessor finishes.
Start to Start: The successor activity cannot start until its predecessor starts.
- Start to Finish: The successor activity cannot finish until its predecessor starts.
Lag Duration (hours) field
The time in hours between the start or finish of the activity and the start or finish of the predecessor successor.
Successor Project ID field
The identifying code of the project that contains the successor activity.
Successor Activity ID field
The identifying code of the successor activity.
Successor Activity Description field
The brief description of the successor activity.
Tips
Asterisks (*) are used in the report to show which activities are contained in closed projects.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule.
- In the Check Schedule dialog box, configure the options and click Check Schedule.
- In the Schedule Check Report dialog box, expand the Links to Closed Projects - Activities with links to closed projects section.
- Click the Actions