Units Columns of the EPS Table

Actual Labor Units field

The labor units expended on the project within the EPS.

Actual Nonlabor Units field

The number of nonlabor units that have been expended on the project within the EPS.

Actual This Period Labor Units field

The number of labor units used during this financial period.

If period performance is stored, the calculation is Actual Labor Units minus the sum of the stored Actual This Period Labor Units fields for all previous periods.

If the period performance is not stored, Actual This Period Labor Units is the same as Actual Labor Units.

Actual This Period Nonlabor Units field

The nonlabor units used during this financial period.

If period performance is stored, the calculation is Actual Nonlabor Units minus the sum of the stored Actual This Period Nonlabor Units fields for all previous periods.

If the period performance is not stored, Actual This Period Nonlabor Units is the same as Actual Nonlabor Units.

At Completion Labor Units field

The sum of the actual plus remaining units for all labor resources assigned to the project.

It is the same as the planned labor units if the activities in the project are not started, and the actual labor units once the activities are completed.

Calculated as Actual Labor Units plus Remaining Labor Units.

At Completion Nonlabor Units field

The nonlabor units at completion. It is the sum of the actual plus remaining units for all nonlabor resources assigned to the activities in the project.

It is the same as the planned nonlabor units if the activities are not started, and the actual nonlabor units once the activities are completed.

Calculated as Actual Nonlabor Units plus Remaining Nonlabor Units.

BL Project Labor Units field

The planned units for all labor resources assigned to the activity in the project baseline.

Calculated as Baseline Actual Labor Units plus Baseline Remaining Labor Units.

BL Project Nonlabor Units field

The units for all nonlabor resources assigned to the project in the project baseline.

Planned Labor Units field

The planned number of units for all labor resources assigned to activities in the project.

Planned Non Labor Units field

The planned units for all non labor resources assigned to the activities in the project.

Remaining Labor Units field

The remaining units for all labor resources assigned to the activities in the project.

The Remaining Labor Units reflect the work remaining to be done for the EPS. Before the project is started, the remaining units are the same as the planned units. After the project is completed, the remaining units are zero.

Remaining Nonlabor Units field

The remaining units for all nonlabor resources assigned to the activities.

The remaining units reflect the work remaining to be done for the EPS.

Variance - Labor Units field

The difference between baseline labor units and at completion labor units.

Calculated as Baseline Labor Units minus At Completion Labor Units.

Variance - Nonlabor Units field

The difference the between baseline nonlabor units and the at completion nonlabor units.

Calculated as Baseline Nonlabor Units minus At Completion Nonlabor Units.



Last Published Wednesday, July 10, 2024