Activity Count Columns of the Activity Table
Activity Count field
The number of activities in the group.
Activity Resource Assignment Count field
The number of assigned resources.
Actual Completed Activities field
The number of activities that have an actual finish date.
Actual In-Progress Activities field
The number of activities that have an actual start date, but no actual finish date.
Actual Not-Started Activities field
The number of activities that have no actual start date.
BL Project Completed Activities field
The number of activities that should currently be completed, according to the project baseline.
BL Project In-Progress Activities field
The number of in-progress activities in the project baseline.
BL Project Not Started Activities field
The number of activities not started in the project baseline.
BL1 Completed Activities field
The number of activities that should be completed according to the primary baseline.
BL1 In-Progress Activities field
The number of activities that should be in progress according to the primary baseline.
BL1 Not Started Activities field
The number of activities that should be not started according to the primary baseline.