Timesheet Feedback Columns of the Activity Table

Feedback from Resource field

The notes received from the resource.

New Feedback option

Determines whether there is new information about this activity which has not yet been reviewed. If the option is not selected, then there is no new feedback or the feedback has already been reviewed.

Review Finish Date field

The finish date for the activity as proposed by the primary resource.

If the project manager approves the activity finish date, the review finish date is copied to the actual finish.

Review Status list

The activity review status.

Primary resources can set the status to For Review when they believe the activity is completed, but a primary resource is not allowed to mark activities as completed.