Baseline Columns of the EPS Table
Baseline Data Date field
The last date of recorded progress for the project baseline. Status is up-to-date as of the data date.
Project Baseline field
The project baseline for the selected project. Published and Summarized data always uses the Project Baseline for Earned Value calculations.