Percent Complete Columns of the EPS Table

Cost % Complete field

The percent complete of costs for all labor resources, nonlabor resources, and expenses for the project.

Calculated as Actual Total Cost divided by At Completion Total Cost multiplied by 100.

Cost % of Planned field

The percent complete of planned costs for all labor resources, nonlabor resources, and expenses for the project.

Calculated as Actual Total Cost divided by Baseline Total Cost multiplied by 100. The value can exceed 100. The baseline total cost is the activity's at completion cost from the current baseline.

Duration % Complete field

The duration percent complete for the project.

Calculated as Planned Duration minus Remaining Duration divided by Planned Duration multiplied by 100. The value is always between 0 and 100.

Duration % of Planned field

The summary actual duration percent of planned duration of all activities for the project.

The baseline duration is the activity's at complete duration from the current baseline.

Calculated as Actual Duration divided by Baseline Duration multiplied by 100. The value can exceed 100.

Expense Cost % Complete field

The percent complete of cost for all expenses associated with project.

Calculated as Actual Expense Cost divided by At Complete Expense Cost multiplied by 100, and it is always in the range of 0 to 100.

Labor Cost % Complete field

The percent complete of cost for all labor resources assigned to a project or EPS.

Calculated as Actual Labor Cost divided by At Completion Labor Cost multiplied by 100. Always in the range 0 to 100.

Labor Units % Complete field

The percent complete of units for all labor resources for the project or EPS.

Calculated as Actual Labor Units divided by At Completion Labor Units multiplied by 100. Always in the range 0 to 100.

Material Cost % Complete field

The percent complete of cost for all material resources assigned to the project or EPS.

Calculated as Actual Material Cost divided by At Complete Material Cost multiplied by 100. Always in the range 0 to 100.

Nonlabor Cost % Complete field

The percent complete of cost for all nonlabor resources assigned to the project and EPS.

Calculated as Actual Nonlabor Cost divided by At Completion Nonlabor Cost multiplied by 100. It is always in the range of 0 to 100.

Nonlabor Units % Complete field

The percent complete of units for all nonlabor resources for the project or EPS.

Calculated as Actual Nonlabor Cost divided by At Completion Nonlabor Cost multiplied by 100. Always in the range 0 to 100.

Performance % Complete field

The percentage of the project planned work that is currently complete.

Performance % Complete is used to calculated earned value and may be based on the Activity % Complete, the 0/100 rule, the 50/50 rule, etc., depending on the technique selected for computing earned value percent complete the WBS elements in the project.

Calculated as Earned Value Cost divided by Budget At Completion multiplied by 100. Always in the range 0 to 100.

Schedule % Complete field

The measure of how much of the project baseline is complete so far.

Calculated as the Planned Value Cost *100 / Budget At Completion Cost.

At the EPS level, Planned Value Cost and Budget At Completion Cost are rolled-up values.

Units % Complete field

The percent complete of units for the resource assignments in the EPS.

The percent complete is always in the range 0 to 100.

Calculated as Actual Units divided by At Complete Units multiplied by 100.