Project Gantt Chart Portlet of the Dashboards Page
Overview
Use this portlet to quickly view the status of projects and review its milestones.
The table lists projects that meet the portfolio, project code value, or project filter criteria specified in the Filter by field in the dashboard. In the table, you can expand the project rows to display a list of each project's start and finish milestone activities. You can filter the milestones that display in the portlet by selecting an activity code filter.
The Gantt chart displays a bar for each project, which represents the span between the Project Planned Start and Scheduled Finish dates of the project. Each project bar indicates current progress, and remaining effort. When you expand a project row in the table to display the project milestone activities, the Gantt chart shows milestone icons for each start and finish milestone activity in the project, and baseline milestones for each start and finish milestone in the baseline if one has been applied to the project.
Screen Elements
Columns field
Enables you to select the data fields you want to display as columns in the current table.
Prints the Grid View.
Filters menu
Select Filter: Opens the select code value dialog box. Select an Activity Code by which to filter.
Clear Filter: Removes the currently set filter and display all milestones.
Expand All button
Enables you to see all of the items in the hierarchical list.
Collapse All button
Enables you to hide subordinate items in the hierarchical list.
ID field
The unique identifier of the project and associated milestones.
This field is fixed and cannot be modified using the customize columns icon.
Name field
The name of the project and associated milestones.
Start field
The start date of the project and its associated milestones.
Scheduled Finish field
The calculated latest early finish date, which is based on the schedule most recently generated for the project.
BL Start field
The current earliest start date of all activities in the project baseline.
BL Finish field
The current latest finish date of all activities in the project baseline.
Project Gantt Chart area
The Current Bar is drawn using the Project Planned Start and Scheduled Finish date fields. Milestones appear as diamonds. The Baseline Bar is drawn underneath the Current Bar using the BL Start and BL Finish dates of the project.
Tip
- Position your mouse pointer over a milestone to view its name and dates.
Getting Here
- Click Dashboards.
- On the Dashboards page, select a dashboard.
- On the dashboard, expand the Project Gantt Chart portlet.
Related Topics
Last Published Wednesday, July 10, 2024