Project Preferences Dialog Box or Default Project Preferences for EPS Dialog Box of the EPS Page
Overview
Use this dialog box to configure project data and settings for the currently open and selected project, its activities, and related items. Select an EPS node to configure the project data and settings for all projects below that node, subject to any filters applied to the view.
You can also use this dialog box to set project preferences to be applied to new projects created in the selected EPS node or to change the default project preferences for an EPS node to that of its parent EPS node.
Note: When you copy or cut and paste a project, the pasted project will retain the preferences of the cut or copied project; it will not inherit the preferences of the EPS node into which it is pasted.
Screen Elements
General tab
See: General Tab of the Project Preferences Dialog Box of the EPS Page
Analytics & Services tab
See: Analytics & Services Tab of the Project Preferences Dialog Box of the EPS Page
Calculations tab
See: Calculations Tab of the Project Preferences Dialog Box of the EPS Page
Integrations tab
See: Integrations Tab of the Project Preferences Dialog Box of the EPS Page
Team Member tab
See: Team Member Tab of the Project Preferences Dialog Box of the EPS Page
Default button
Changes all settings for the currently selected EPS node to the default settings for the application. Any settings changed from their previous values will be highlighted so that you can choose to Save or Cancel the changes to the selected EPS node's default project preferences. This option is only available in the Default Project Preferences for EPS dialog box.
Inherit EPS Project Preferences button
Changes all settings for the currently selected EPS node to the settings of its parent EPS node. Any settings changed from their previous values will be highlighted so that you can choose to Save or Cancel the changes to the selected EPS node's default project preferences. This option is only available in the Default Project Preferences for EPS dialog box.
Save button
Saves the changes you made to the currently selected EPS node's default project preferences. Projects created in the selected EPS node in the future, will use the saved settings.
Apply button
Project Preferences dialog box: Applies the changes you made to the selected project's preferences.
Default Project Preferences for EPS dialog box: Applies the changes you made to the project preferences of all visible projects and EPS nodes in the selected EPS node and all their children. If
Getting Here
- Click Projects.
- On the Projects navigation bar, click EPS.
- Select a project or EPS node, click the Row Actions menu and select Set Project Preferences.
Related Topics