Gantt tab of the Manage Views Dialog Box of the Activities Page, EPS Page or Assignments Page
Overview
Use this tab to configure progress lines and timescale for the Gantt chart.
Screen Elements
Show section
Data date line option
Determines whether to show the data date as a vertical line in the Gantt Chart.
Relationship lines option
Determines whether to show lines to represent the relationships between different activities.
Non-driving relationships option
Determines whether to show lines for relationships which do not drive the dates of successor activities. To see the Non-driving relationships option, select the Relationship Lines option.
Sight lines option
Determines whether to show lines for relationships which do not drive the dates of successor activities.
Note: The Data date line, Relationship lines, and Sight Lines options are available in the Gantt tab of the Manage Views dialog box in the Activities page. The Non-driving relationships option is available in the Gantt tab of the Manage Views dialog box in the Activities and EPS pages.
Non-work time shading option
Determines whether to shade non-work time in the project default calendar on the Gantt chart.
Timescale section
Timescale list
The Gantt chart time interval options. Select from one of the following intervals:
Week/Day: The Gantt View is divided into weeks which are then divided into days.
Month/Week: The Gantt View is divided into months which are then divided into weeks.
Quarter/Month: The Gantt View is divided into quarters which are then divided into months.
Year/Month: The Gantt View is divided into years which are then divided into months.
Year/Quarter: The Gantt View is divided into years which are then divided into quarters.
Financial Period: The Gantt chart is divided into years which are then divided into financial periods.
Financial Period Calendar list
The financial period calendar you want to use when showing Financial Period as the timescale in the Gantt and the Resource and Role Assignment dialog box. To see this field, select Financial Period on the Timescale list.
Getting Here
- Click Projects or Resources.
- On the Projects navigation bar, click Activities, EPS, or Assignments.
- On the Resources navigation bar, click Assignments.
- Click the Views
menu and select Manage Views....
- In the Manage Views dialog box, click Gantt.