Resources Tab of the Level Resources Dialog Box of the Activities Page
Overview
Use this tab to specify which resources to level.
Screen Elements
All resources / Selected resources option
Determines whether all resources or only the resources you select are leveled.
Available
The list of resources available to level.
Search
Enables you to perform a search based on the value you enter in the search bar.
Selected
The list of resources you selected from the available resources.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Leveler.
- In the Level Resources dialog box, click the Prioritization tab.