Risks Detail Window of the Activities Page

Overview

Use this detail window to assign and configure risks.

Screen Elements

Add

Adds a new row to the list.

Assign... button

Opens the Select Risk dialog box.

Customize View

Opens the Customize View dialog box.

Row Actions menu

Add: Adds a new item to the list.

Delete: Deletes the selected item.

Risks detail window columns

Only the default fields that appear as columns in the Risks detail window are described below.

Name field

The name for a particular type of risk classification.

ID field

The unique identifier for the risk.

Name field

The name of the risk.

Owner field

The resource who has ownership of the risk.

Schedule Impact (net) field

The net impact on the schedule if the risk occurs.

Status field

The current state of the risk.

Proposed: The risk is identified and awaits approval.

Open: The risk is approved as a valid risk to the project.

Active: The risk is currently impacting the project.

Rejected (Closed): The risk is not seen as a valid risk to the project and therefore will not be tracked and managed by the project. The data for this risk cannot be modified once it is closed.

Managed (Closed): The risk occurred and was successfully managed by the project team and is no longer an active risk. The data for this risk cannot be modified once it is closed.

Impacted (Closed): The risk occurred, impacted the project and is no longer an active risk. The data for this risk cannot be modified once it is closed.

Status Indicator field

A graphical indicator showing the status of the risk.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. Select an activity and click the Risks detail window.

Related Topics

About Activities

Working with Activities

Creating Activities

About Risks