Gantt View Format of the EPS Page
Overview
Use the Gantt chart format to view project duration, dates, and progress in an EPS node.
Screen Elements
Right-clicking on the timescale will display:
Timescale list
The Gantt chart time interval options. Select from one of the following intervals:
Week/Day: The Gantt View is divided into weeks which are then divided into days.
Month/Week: The Gantt View is divided into months which are then divided into weeks.
Quarter/Month: The Gantt View is divided into quarters which are then divided into months.
Year/Month: The Gantt View is divided into years which are then divided into months.
Year/Quarter: The Gantt View is divided into years which are then divided into quarters.
Financial Period: The Gantt chart is divided into years which are then divided into financial periods.
Zoom to fit: Adjusts the current view's height and width or timescale to fit as much of the data as possible into the current work area.
Note: If you select to show the Financial Periods timescale, you can hover over a financial period in the timescale to see the start and finish dates of the financial period.
Hovering over a project bar will display:
Name field
The name of the project.
Bar Types field
The type of bar shown in an EPS view Gantt chart.
Current Bar: Spans the early remaining/actual start to the early remaining/actual finish for each activity, and indicates how the schedule is progressing according to the original plan.
Project Baseline Bar: Shows the project baseline start and finish dates of an activity, and indicates how the schedule is progressing according to the original plan.
Forecast bar: Shows the forecast start to the forecast finish dates, and indicates how the schedule is progressing according to the original forecast dates.
Start Date field
The current start date of the project. For a not started project, this is the project's planned start date. For a project that has started or is complete, this is the project's actual start date. For projects with no activities, the start date is equal to the anticipated start date if one is defined; if no anticipated start is defined, then the start date is equal to the project's planned start date.
Finish Date field
The current finish date of the project. For not started and in-progress projects, this is the latest early finish date from all activities in the project. For completed projects, this is the latest actual finish date derived from all activities. For projects with no activities, the Finish Date is equal to the Anticipated Finish date if one is defined. For projects with no activities and no Anticipated Finish date, the Finish Date field is blank.
Show Legend
Enables you to view a description of the currently defined bars available on the Gantt chart. To hide the legend, click Hide Legend
Gantt Settings
Enables you to show or hide elements of the Gantt.
Sight Lines Show or hide vertical sight lines in the Gantt.
Timescale Select a timescale for the Gantt.
Tips
- If financial periods do not exist for part of the duration of your project, the Gantt chart does not show data for the parts of your project whose dates fall outside the existing financial periods.
- If financial periods do not exist for the whole of the duration of your project, the Gantt chart does not show any data. Change the Gantt timescale for your view in the Manage Views dialog box.
- You cannot zoom the financial period Gantt timescale using Zoom to Fit, nor by dragging the timescale.
Getting Here
- Click Projects.
- On the Projects navigation bar, click EPS.
- Click Gantt View.
Related Topics
Last Published Wednesday, July 10, 2024