EPS General Detail Window of the EPS Page
Overview
Use this detail window to add or modify information about the selected EPS element.
Screen Elements
EPS field
An identifier that is unique to the EPS node.
EPS Name field
The name of the EPS.
Responsible Manager field
The organization breakdown structure (OBS) assigned to the project or EPS.
Planned Dates section:
Anticipated Start field
The expected start date of the project used during the planning phase. This date is manually entered and is not affected by scheduling.
If there are no children elements, the anticipated start is the start date listed for the project in the table.
Anticipated Finish field
The expected finish date of the project used during the planning phase. This date is manually entered and is not affected by scheduling.
If there are no children elements, the anticipated finish is the finish date listed for the project in the table.
Tips
- If you have more than one EPS selected, the detail window will not be visible.
- EPS detail windows appear only when you group the EPS view by all EPS levels and select an EPS.
Getting Here
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page, select an EPS node and click the General detail window.