EPS General Detail Window of the EPS Page

Overview

Use this detail window to add or modify information about the selected EPS element.

Screen Elements

EPS field

An identifier that is unique to the EPS node.

EPS Name field

The name of the EPS.

Responsible Manager field

The organization breakdown structure (OBS) assigned to the project or EPS.

Planned Dates section:

Anticipated Start field

The expected start date of the project used during the planning phase. This date is manually entered and is not affected by scheduling.

If there are no children elements, the anticipated start is the start date listed for the project in the table.

Anticipated Finish field

The expected finish date of the project used during the planning phase. This date is manually entered and is not affected by scheduling.

If there are no children elements, the anticipated finish is the finish date listed for the project in the table.

Tips

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page, select an EPS node and click the General detail window.