Issues Detail Window of the EPS Page
Overview
Use this detail window to list and manage issues associated with the selected project.
Screen Elements
Add button
Adds an item to the table.
Customize View
Opens the Customize View dialog box.
Issues table area:
Row Actions menu
Delete: Deletes the selected item.
Issue Name field
The name of the project issue.
In P6 Professional, issues which are automatically generated by the threshold monitor are named after the threshold parameter that triggered the project issue.
Priority list
Determines the priority of the activity when performing resource leveling.
Status field
The current status of the issue.
Owner field
The resource who is responsible for the issue.
Responsible Manager field
The organizational breakdown structure (OBS) assigned to the issue.
If the field is editable and you have edit privileges, you can select a different responsible manager.
Description field
A detailed summary for the item.
The description provides more information than short names or titles. It can give background information or establish a purpose for the item. These details help differentiate between items with similar names and are especially useful in multi-user environments.
Tips
- If you have a project template open, the icons in the detail window will be disabled.
- If more than one project is selected, the detail window will not be visible.
Getting Here
- Click Projects.
- On the Projects navigation bar, click EPS.
- Select a project and click the Issues detail window.
Related Topics
Last Published Wednesday, July 10, 2024