Activity Tab of the UN/CEFACT Template Dialog Box of the Import/Export Project Dialog Box
Overview
Use the Activity tab of the Add/Modify Template dialog box to specify activity data to be exported to a UN/CEFACT file.
Screen Elements
Template Name field
The name for the import or export template.
This field is required and can contain up to 40 characters.
Notes tab:
Add Notes... button
Adds a note item to the list.
Note list
The type for the note field.
Content list
The project notebook topic to export as the selected note type the file.
Miscellaneous tab:
RiskLevelDescription list
The UDF to export as the Risk Level Description.
PriorityRankingNumeric list
The UDF to export as the Priority Ranking Numeric.
EarnedValueMethodCode list
The UDF to export as the Earned Value Method Code.
ScheduleLevelNumeric list
The UDF to export as the Schedule Level.
MileStoneWeightNumeric list
The UDF to export as the Milestone Weight.
ControlAccountID list
The UDF to export as the Control Account ID.
ScheduleLevel list
The UDF to export as the Schedule Level.
WorkPackageID list
The UDF to export as the Work Package ID.
PlanningLevelCode list
The UDF to export as the Planning Level Code.
Dates and Durations tab:
Note: The following fields are repeated in three groupings, for Best Case, Most Lkely and Worst Case.
Duration list
The field to export as the duration.
Note: In addition to User Defined Duration fields, the Duration list includes:
- Minimum Duration as caulcuated by Risk Analysis for the Best Case duration.
- Maximum Duration as caulcuated by Risk Analysis for the Most Likely duration.
- Most Likely Duration as caulcuated by Risk Analysis for the Worst Case duration.
Early Start Date list
The user defined Start Date field to be exported as the Early Start Date.
Early Finish Date list
The user defined Finish Date field to be exported as the Early Finish Date.
Late Start Date list
The user defined Start Date field to be exported as the Late Start Date.
Late Finish Date list
The user defined Finish Date field to be exported as the Late Finish Date.
Getting Here
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page, click the Actions
menu and select Import/Export Projects.
- In the Import/ExportProject dialog box, click the Export tab.
- Or on the Export tab:
- In the Export Type list, select UN/CEFACT XML Format 6.
- In the Project field, click Browse and select a project.
- Click Manage Templates.
- Or on the Export tab:
- In the Manage Templates dialog box, click a template.
- In the UN/CEFACT Template dialog box, click the Activity tab.
Related Topics
About Importing and Exporting Projects
Configuring UN/CEFACT Templates
Last Published Wednesday, July 10, 2024