Recalculate Assignment Costs Dialog Box of the Activities Page

Overview

Use this dialog box to update price per time values on activities. This ensures that project costs reflect any updates.

Screen Elements

Synchronize overtime factor while recalculating costs option

Determines whether the overtime factors will be synchronized when costs are recalculated.

Recalculate button

Recalculates assignment costs for all open projects and closes the Recalculate Assignment Costs dialog box.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. Click Actions and select Recalculate Assignment Costs.

Related Topics

About the Recalculate Assignment Costs Feature

About Resource Assignments

Specifying Resource Assignment Rates

About Earned Value

About Financial Periods

About Future Period Planning