Activity Data Tab of the Update Baselines Dialog Box of the Activities Page or EPS Page
Overview
Use this tab to determine which activities should be updated in the baseline.
Screen Elements
Specify the activities to include option
Select from one of the following options to determine which activities in the baseline should be updated.
All Activities: Select to update all the activities in the baseline. All activities in the baseline will be overwritten.
Activities within the following filters: Select whether to update activities within all or any of the selected filters.
selected filters: Select a filter from the list.
To overwrite all activity data, select All Activities and all of the activity data options on the Update Options tab.
If you choose to update activities that fall within a filter and choose to add new activities, only activities that meet that filter's criteria will be added.
Add new activities and activity data (except actuals) option
Determines whether to add to the baseline activities that exist in the project but not the baseline.
Delete from baseline any activities no longer in the current project option
Determines whether to remove activities from the baseline if there is no longer a matching activity in the project.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities or EPS.
- On the Activities or EPS page, click the Actions
menu and select Define Baselines.
- In the Define Baselines dialog box, select a baseline and click Update.
- Select the Activity Data tab.
Related Topics
Last Published Wednesday, July 10, 2024