Activity Network Format of the Activities Page

Overview

Use the Activity Network format to view activities and their relationships as a network.

Screen Elements

Activity Network work area

The area in which you can view the activity network.

Activity boxes outlined in red are critical activities; activity boxes outlined in black are not critical activities. Solid red lines between boxes represent critical relationships, while black lines represent non-critical relationships. Solid lines represent driving relationships, while dashed lines represent non-driving relationships. The selected box has a heavy blue border. Boxes with a black diamond in the corner represent milestones. A status icon in the corner of the box identifies In Progress, Completed, and Critical activities.

Activity boxes show the Activity Name, Activity ID, Start Date and Finish Date. You cannot customize activity boxes in Standard View.

Floating Toolbar

Toolbar Handle: Enables you to drag the toolbar to a new location.

Zoom In: Magnifies items in the work area so they appear larger.

Zoom Out: Minimizes items in the work area so they appear smaller.

Zoom to 100%: Restores the magnification of the current work area to its default size of 100%.

Zoom to Fit: Adjusts the height and width or timescale of the current view to fit as much of the data as possible into the current work area.

Show Driving Relationships: Hides non-driving relationships.

Show Critical Activities: Dims all activities which are not critical.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. Click Activity Network View.