Trace Logic Detail Window of the Activities Page
Overview
Use this detail window to view activity relationships using trace logic.
Screen Elements
Zoom In
Magnifies items in the work area so they appear larger.
Zoom Out
Minimizes items in the work area so they appear smaller.
Zoom to 100%
Restores the magnification of the current work area to its default size of 100%.
Zoom to Fit
Adjusts the height and width or timescale of the current view to fit as much of the data as possible into the current work area.
Predecessor Levels field
The number of predecessor levels to show for the selected activity.
Successor Levels field
The number of successor levels to show for the selected activity.
Trace Logic work area
The area in which you can view and trace logic relationships.
Activity boxes outlined in red are critical activities. Solid red lines between boxes represent critical relationships. Solid lines represent driving relationships, while dashed lines represent non-driving relationships. The selected box has a heavy blue border. Boxes with a black diamond in the corner represent milestones. A status icon in the corner of the box identifies In Progress, Completed, and Critical activities.
Activity boxes show the Activity Name, Activity ID, Start Date and Finish Date. You cannot customize activity boxes in Standard View.
Tips
If you have more than one activity or a grouping band selected, the detail window will not be visible.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Select an activity and click the Trace Logic detail window.
Related Topics