Converting Classic Views to Standard Views

From release 18, classic views are no longer available in P6. You can export classic views to import them as standard views. When you import the exported classic views, they are imported as user views. To make the newly imported views accessible to other users, you can cut or copy and paste the views to the Global or Multiple Users groups.

Note: Although classic views can no longer be used from release 18, they are not removed from the database during the upgrade process and can still be exported after upgrade.

To convert classic views to standard views:

  1. Click Projects or Resources.
    • On the Projects navigation bar, click Activities, EPS, or Assignments.
    • On the Resources navigation bar, click Assignments.
  2. Click the Views menu and select Import/Export Views....
  3. In the Import/Export Views dialog box:
    1. Click Export.
    2. Select the Classic Views option.
    3. Select the views you want to export.
    4. Click Export.
  4. Click the Views menu and select Import/Export Views....
  5. In the Import/Export Views dialog box:
    1. Click Import.
    2. In the File field, click Browse and select the file you exported.
    3. Select the views to import.
    4. Click Import.

Tips:

Related Topics

Configuring Activity Views

Configuring Activity View Columns

Configuring Activity View Grouping

Configuring Activity View Filters

Configuring Activity View Gantt Chart Bars

Configuring Activity View Gantt Chart

Configuring Activity Network

Configuring Activity View Access