Warnings Section of the Schedule Project Log Dialog Box of the Activities Page
Overview
Use this section to view warnings for various projects.
Screen Elements
Activities without predecessors and Activities without successors tables
The information about the activities that do not have predecessors or successors in a table format.
Project ID: The unique identifying code for the project associated with the activity.
Project Name: The name of the project associated with the activity.
Activity ID: The unique identifier of the activity.
Activity Name: The name of the activity.
Start: The current start date of the activity.
Finish: The current finish date of the activity.
Out of sequence activities table
The activities that have started before their predecessor activity has completed in a table format.
Project ID: The unique identifying code for the project associated with the activity.
Project Name: The name of the project associated with the activity.
Activity ID: The unique identifier of the activity.
Activity Name: The name of the activity.
Start: The current start date of the activity.
Finish: The current finish date of the activity.
Activities with actual date later than data date table
The activities in which the data date is before the actual date in a table format.
Project ID: The unique identifying code for the project associated with the activity.
Project Name: The name of the project associated with the activity.
Activity ID: The unique identifier of the activity.
Activity Name: The name of the activity.
Start: The current start date of the activity.
Finish: The current finish date of the activity.
Milestones with invalid relationships table
The milestones which were found to have invalid relationships during the scheduling or leveling process in a table format.
Project ID: The unique identifying code for the project associated with the activity.
Project Name: The name of the project associated with the activity.
Activity ID: The unique identifier of the activity.
Activity Name: The name of the activity.
Start: The current start date of the activity.
Finish: The current finish date of the activity.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, and click Schedule... (F9).
- In the Schedule dialog box:
- Configure the options and select the Display scheduling log upon completion option.
- Click Schedule Now.
Last Published Wednesday, July 10, 2024