Exceptions Section of the Schedule Project Log Dialog Box of the Activities Page

Overview

Use this section to view the number of critical activities, activities with unsatisfied constraints, activities with unsatisfied relationships, and activities with external dates.

Screen Elements

Critical Activities field

The number of critical activities in the selected project.

Activities with unsatisfied constraints field

The number of activities with constraints that have not been addressed.

Activities with unsatisfied relationships field

The number of activities with relationships that have not been addressed.

Activities with external dates field

The number of activities with external dates.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, and click Schedule... (F9).
  4. In the Schedule dialog box:
    1. Configure the options and select the Display scheduling log upon completion option.
    2. Click Schedule Now.


Last Published Wednesday, July 10, 2024