Updating Progress on Steps

Update your steps to record your progress.

To update progress on a step:

  1. Select an activity.
  2. On the Activity Details tab of the progress panel:
    1. Expand the Steps section.
    2. Select More (Ctrl+Alt+M) to view all steps, if all steps are not visible.
    3. In the % Complete field, enter a percentage value for your work complete.
    4. Optionally view and change the values for user defined fields associated with the step.
    5. If you are finished with the step, either:
      • Enter 100 in the percentage field.
      • Select Complete Step (Ctrl+Alt+C).
    6. Select Save (Ctrl+Alt+Enter).

Tips

Step me through...

Adding Steps

Learn more about...

Steps

Working with Steps

Working with Activities