Burn Down Activity Scenarios
The following topics show individual activity use case details for different Burn Down project activity states.
The following assumptions are made for the activity use cases:
- sys_workdown_date: The project schedule uses a sys_workdown_date of 3/31/2013.
- Data Date: This is equal to the project's Data Date when the ETL process is run.
- ETL Process Date: The ETL process is run each day no later than 11:59 p.m. and after the schedule is updated and the Data Date is advanced.
To properly calculate Burn Down metrics, the schedule must be updated and the ETL process must be run daily.
Related Topics
Completed Before Outage Project Snapshot Use Case
Started Before Outage Project Snapshot Spanning into Outage Use Case
Completed Day of Outage Project Snapshot Use Case
Pre-Outage Work Spanning into Outage Use Case
Completed as Scheduled on Day 1 of Outage Use Case
Completed Late on Day 3 of Outage Use Case
Emergent Activity on Day 3 of Outage Use Case
Deleted After Outage Start Use Case