Modifying an Existing Budget

To create a budget change request:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page, select an EPS or project and click the Budget Log detail window.

    Note: You can also create budget change requests for a project or WBS element from the Budget Log detail window of the Activities page.

  4. In the Budget Log detail window:
    1. Click Add (Ins) to add a budget log line item.
    2. In the Amount field, enter a currency value.
    3. In the Responsible field, enter the name of the responsible person or department.
    4. In the Status list, select a status value for the proposed change.
  5. On the EPS page, click Save.

Tips

Related Topics

Managing Budgets

Viewing Budgets

Adding Budgets



Last Published Tuesday, November 26, 2024