Configuring Risk Enterprise Data
You can configure enterprise data to include risk categories and risk UDFs, and to define the criteria for performing qualitative risk analysis using a risk scoring matrix.
To define the criteria for performing qualitative risk analysis, perform the following tasks:
- Creating Risk Thresholds
- Creating Risk Scoring Matrices
- Assigning a Risk Scoring Matrix to a Project
Note: If you want to perform quantitative risk analysis in Oracle Primavera Cloud, you must also populate the Minimum Duration, Maximum Duration, and Most Likely Duration fields in the Activities view.
To configure risk categories or risk UDFs, perform the following tasks: