Configuring Activity Code Values
Configure activity code values to reflect changing variations within the larger scope of the activity code.
To configure activity code values:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Activities and click Activity Codes - EPS, Activity Codes - Global, or Activity Codes - Project.
- On the Activity Codes - EPS, Activity Codes - Global, or Activity Codes - Project page, select an activity code value.
- In the Name field, double-click and type a name for the code value.
- In the Description field, double-click and type a brief narrative about the code value.
- In the Color field, double-click and select a color.
Note: In the Gantt chart and the Activity Calendar, activity status shown by activity code will display the color you apply to the activity code value.
- On the Activity Codes page, click Save.
Tips
- Activity code values at the same level are siblings. Subordinate activity code values are children.
- You can also configure activity code values from the Codes detail window on the Activities page.
- If you are working on the Activity Codes - Project page and the project you need is not visible, click Open Project. In the Open Projects dialog box, select a project from the Available Projects list, click to move the project to the Selected Projects list, and click OK.