Adding Risk Response Plans
Add one or more response plans to a risk to plan alternative activities that might reduce the probability of a risk occurring, or to reduce the impact of the risk.
- Click Projects.
- On the Projects navigation bar, click Risks.
- On the Risks page, click a risk, and then click the Response Plans detail window.
- On the Response Plans detail window:
- Click Add and select Response Plan.
- In the ID field, double-click and type a response plan ID.
- In the Name field, double-click and type a name for the new response plan.
- In the Response Type field, double-click and select a response type from the list.
- On the Risks page, click Save.
Note: After you decide which response plan you are implementing, select the Active option next to the appropriate response plan.
Related Topics
Assigning a Risk to an Activity
Working with Risk Response Plans
Developing a Risk Response Plan
Adding Risk Response Plan Action Items
Assigning Activities to Risk Response Plan Action Items
Last Published Tuesday, March 26, 2024