Adding Project Risks to Activities
Managing the Schedule > Risks > Working with Project Risks > Managing Project Risks > Creating Project Risks
Add project risks to activities to capture potential threats or opportunities that might impact your project. Use this method if you want to quickly associate a risk to an activity. You can add a new project risk to an activity, or assign an existing project risk to an activity.
To add a new or assign an existing project risk to an activity:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity and click the Risks detail window.
- To assign an existing risk to the activity, in the Risks detail window click Assign....
- In the Select Risk dialog box click on a risk and then click Assign.
- To add a new risk to an activity, in the Risks detail window click Add.
- To assign an existing risk to the activity, in the Risks detail window click Assign....
Related Topics
Adding Detailed Project-Level Risks
Adding High-Level Project Risks