Configuring Activity Resources
You can configure resource information for activities, including the Planned Units/Time, Proficiency, or Rate Type for a resource.
To configure activity resources:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity and click the Assignments detail window.
- In the Assignments detail window:
- Select a resource.
- Add or remove the columns you need to configure to the detail window.
- Select an option or enter a value for each field.
Tips
- You can also configure activity resources from the Open Requests for Resources portlet of the Dashboards page.
- When you create, delete, or modify a resource assignment, your changes are automatically saved when you select another activity. You will not be able to undo the changes after selecting a different activity.
Related Topics
Assigning Resources to an Activity
Specifying Resource Assignment Rates
Adding Activity Resource Estimates
Showing or Hiding Columns in a Table