Creating Activity Relationships
You can create activity relationships in the Gantt chart to show interdependencies between activities.
To create an activity relationship:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Gantt View.
- Click Gantt Settings and select to show relationships.
- Hover either to the left or right of a bar.
- Drag the circle to the left or right end of a bar representing the activity you want to link.
Note: Where you drag the relationship on each bar determines the type of relationship.
- Click Save.
Tips
- You can scroll through the Gantt chart while while dragging a relationship to find a related bar.
- To delete a relationship, right-click the relationship line and select Delete Relationship.
- If multiple projects are open, you can create external relationships.
- You can also create new relationships and view or configure existing predecessor or successor relationships, from the Relationships detail window.
Related Topics
Configuring Activity Relationships
Assigning Predecessor Relationships
Configuring Predecessor Relationships
Assigning Successor Relationships
Configuring Successor Relationships