Dangling Start - Activities With Start Dates That Are Not Driven by Predecessors Section of the Schedule Check Report Dialog Box

Overview

Use this section to identify activities with start dates that are not driven by the activity's predecessors. If an activity's start date is not driven by its predecessors that activity can cause inaccuracies in the schedule and critical path calculation as well as affecting the calculations of milestones and completion dates.

Screen Elements

Project ID field

The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.

Activity ID field

The unique identifying code for the activity which failed the check. Click this link to view the activity.

Activity Name field

The name of the listed activity. Click this link to view the activity.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. Click the Actions menu and select Check Schedule, then select View Report.


Last Published Wednesday, November 27, 2024