Adding Activity Resource Estimates
You can plan resource usage by adding resource estimates to activities.
To add resource estimates:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity and click the Assignments detail window.
- In the Assignments detail window:
- Assign a resource or role to the selected activity.
- Add the Planned Units/Time, Planned Units, Planned Cost, and Planned Duration columns to the detail window.
- Select an option or enter a value for each field.
Related Topics
Assigning Resources to an Activity
Assigning Resources to Multiple Activities
Configuring Activity Resources
Specifying Resource Assignment Rates
Assigning Resource Curves to Resource or Role Assignments from the Activities Page
Assigning Resources to Unstaffed Activities
About the Recalculate Assignment Costs Feature
Configuring Resource Leveling Options and Priorities
About the Check Resource Overallocation Service
Assigning Resources to an Activity
Assigning Roles to an Activity
Showing or Hiding Columns in a Table
Last Published Thursday, October 3, 2024