Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page
You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.
To assign a resource curve:
- Click Resources.
- On the Resources navigation bar, click Assignments.
- On the Assignments page:
- Display the Curves column if it is not visible on the table. To display the Curves column, click Customize View and click Columns, expand the General grouping and double-click Curve to move it to the Selected Columns list.
- On the Assignments page:
- Click the row with the resource or role.
- Double-click the Curve field, and clickSelect .
- In the Select Curves dialog box, choose a curve and click OK.
- On the Assignments page, click Save.
Tips:
- You can also assign resource curves to resource or role assignment from the Activities page.
Related Topics
Working with Resource Assignments in the Gantt Chart
Viewing Assignment Unit and Cost Spreads
Assigning a Resource to an Activity Assignment
Assigning Resource Curves to Resource or Role Assignments from the Activities Page
Last Published Thursday, October 3, 2024