Standard Work Week Tab of the My Calendar dialog box or Resource Calendars Page
Overview
Use this tab to specify the length of work hours in a day or to calculate the total number of hours worked in a particular day.
Screen Elements
Opens the Print Options dialog box.
Total Hours field
The total number of work hours for each day.
Calendar View area
Enables you to view a day, week, month, or year of the calendar to identify standard time, nonwork time and calendar exceptions.
Work Period display
Displays a box that represents each work period in a day. If you change the number of hours covered by the work period boxes for a day, P6 updates the Total Hours field.
Tips:
- You can change the Starting Day of Week setting in the General tab of the Application Settings page.
Getting Here
From the Enterprise Data page:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Resources and click Resource Calendars.
- On the Resource Calendars page, click the Standard Work Week tab.
From the My Calendar dialog box:
- Click the User menu and select My Calendar.
- In the My Calendar dialog box, select the Standard Work Week tab.
Related Topics
Configuring Resource Calendars
Assigning a Base Calendar to a Resource Calendar
Assigning a Resource to a Resource Calendar
Setting Work Hours Per Time Period for a Resource Calendar
Configuring the Standard Work Week for Resource Calendars