Configuring Activity Relationships
Configure activity relationships to adjust interdependencies between different activities.
To configure activity relationships:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click Gantt View.
- Click Gantt Settings and select to show relationships.
- Right click the relationship line of the relationship you want to configure and click Edit Relationship.
- In the Edit Relationship dialog box, configure the type and lag and click Apply.
- On the Activities page, click Save.
Tips
You can also configure predecessor and successor relationships from the Relationships detail windows.
Related Topics
Creating Activity Relationships
Assigning Predecessor Relationships
Configuring Predecessor Relationships
Assigning Successor Relationships
Configuring Successor Relationships
Configuring Predecessor Relationships
Configuring Successor Relationships