Invalid Progress Dates - Activities with Actual Dates After the Data Date Section of the Schedule Check Report Dialog Box

Overview

Use this section to view activities that have actual dates after the data date.

Only a subset of the activities in the open projects are checked. WBS summary activities, Level of Effort activities, and activities with actual finish dates before the data date are removed from the subset to create the list of activities checked for actual start or finish dates occurring after the data date. The Actual percentage is calculated as the number of activities found that match the check divided by the number of subset activities checked.

Screen Elements

Project ID field

The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.

Activity ID field

The unique identifying code for the activity which failed the check. Click this link to view the activity.

Activity Name field

The name of the listed activity. Click this link to view the activity.

Data Date field

The progress point, or "as-of date", for activities in the project. Project status is up-to-date as of the data date. You can set the data date when you schedule the project or apply actuals, or you can set it manually. Set it manually if resources manually update activity progress and you do not plan to reschedule the project or apply actuals.

Actual Start Date field

The date the activity started.

Actual Finish field

The date on which the activity was completed.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. Click the Actions menu and select Check Schedule, then select View Report.

Related Topics

About Scheduling Projects