Large Durations - Activities That Have a Remaining Duration Greater Than 352 Hours Section of the Schedule Check Report Dialog Box

Overview

Use this section to view activities with duration greater than the value you listed in the Large Durations field in the Check Schedule dialog box. Activities with a large duration are difficult to manage. You can break these activities down into smaller activities which provide a better insight into cost and schedule.

Only a subset of the activities in the open projects are checked. WBS summary activities, activities with an actual finish date, milestones, and Level of Effort activities are removed from the subset to create the list of activities checked for large remaining duration. The Actual percentage is calculated as the number of activities found that match the check divided by the number of subset activities checked.

Screen Elements

Project ID field

The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.

Activity ID field

The unique identifying code for the activity which failed the check. Click this link to view the activity.

Activity Name field

The name of the listed activity. Click this link to view the activity.

Remaining Duration (hours) field

The time left to complete an activity in hour format.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
    1. Click the Actions menu and select Check Schedule, then select View Report.