Large Durations - Activities That Have a Remaining Duration Greater Than 352 Hours Section of the Schedule Check Report Dialog Box
Overview
Use this section to view activities with duration greater than the value you listed in the Large Durations field in the Check Schedule dialog box. Activities with a large duration are difficult to manage. You can break these activities down into smaller activities which provide a better insight into cost and schedule.
Only a subset of the activities in the open projects are checked. WBS summary activities, activities with an actual finish date, milestones, and Level of Effort activities are removed from the subset to create the list of activities checked for large remaining duration. The Actual percentage is calculated as the number of activities found that match the check divided by the number of subset activities checked.
Screen Elements
Project ID field
The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.
Activity ID field
The unique identifying code for the activity which failed the check. Click this link to view the activity.
Activity Name field
The name of the listed activity. Click this link to view the activity.
Remaining Duration (hours) field
The time left to complete an activity in hour format.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions