Relationship Types - The Majority of Relationships Should be Finish to Start Section of the Schedule Check Report Dialog Box
Overview
Use this section to view the percentage of each relationship type in the schedule. To ensure schedule stability, the majority of relationships should be Finish to Start.
Only a subset of all the internal and external links in the open projects are checked. Any links between activities that both have actual finish dates are removed from the subset to create the list of links checked for relationship type. The Actual percentage is calculated as the number of links found that match the check divided by the total number of subset links checked.
Screen Elements
Relationship Type field
The type of relationship between two activities.
Valid values are:
Finish to Start: The successor activity cannot start until its predecessor finishes.
Finish to Finish: The successor activity cannot finish until its predecessor finishes.
Start to Start: The successor activity cannot start until its predecessor starts.
Start to Finish: The successor activity cannot finish until its predecessor starts.
Count field
The number of relationships of that type.
% field
The percentage of that type of relationship.
Calculated as the number of relationships of a certain type divided by total relationships checked.
Predecessor Project ID field
The identifying code for the project containing the predecessor activity that failed the check. Click this link to view the predecessor project.
Predecessor Activity ID field
The identifying code for the predecessor activity that failed the check. Click this link to view the predecessor activity.
Predecessor Activity Description field
The brief description of the predecessor activity. Click this link to view the predecessor activity.
Lag Duration (hours) field
The time in hours between the start or finish of the activity and the start or finish of the predecessor successor.
Successor Project ID field
The identifying code of the project that contains the successor activity. Click this link to view the successor project.
Successor Activity ID field
The identifying code of the successor activity. Click this link to view the successor activity.
Successor Activity Description field
The brief description of the successor activity. Click this link to view the successor activity.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions