Relationships - Activities Missing Predecessors or Successors Section of the Schedule Check Report Dialog Box
Overview
Use this section to identify activities missing a predecessor, successor, or both. This indicates how well or poorly the schedule is linked together.
Only a subset of all the activities in the open projects are checked. WBS summary activities and activities with an actual finish date are removed to create the list of activities that are checked for missing logic. In the logic check, activities with an actual start or that are Start Milestones pass the predecessor check even if they do not have a predecessor. Finish Milestone activities always pass the successor check even if they do not have a successor. Activities with external predecessors or successors pass the check. Any of the remaining activities that were found to not have a predecessor or successor are then reported in the check. The Actual percentage is calculated as the number of activities found that match the check divided by the number of subset activities checked.
Screen Elements
Project ID field
The unique identifying code of the project containing the activity which failed the check. Click this link to view the project.
Activity ID field
The unique identifying code for the activity which failed the check. Click this link to view the activity.
Activity Name field
The name of the listed activity. Click this link to view the activity.
State field
The items that the listed activity is missing, whether predecessor, successor, or both.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Activities.
- Click the Actions
menu and select Check Schedule, then select View Report.
- Click the Actions