Percent Complete Columns of the Activity Table
Activity % Complete field
The percent of the activity that has been completed.
The calculation is based on the formula for the selected Percent Complete Type. The Percent Complete Type can be Units, Duration, Physical, or Scope.
If the selected activity's percent complete type is Duration, the percent complete is calculated as (Planned Duration minus Remaining Duration) divided by Planned Duration.
If the activity's percent complete type is Units, the percent complete is calculated as (Actual Labor Units plus Actual Nonlabor Units) divided by (Actual Labor Units plus Actual Nonlabor Units plus Remaining Labor Units plus Remaining Nonlabor Units).
If the activity's percent complete type is Physical, either the user records the percent complete manually or the field is set to calculate using steps. To calculate using steps, the Calculate Activity % Complete from activity steps option must be set in Project Preferences.
If the activity's percent complete type is Scope, the percent complete is calculated by Oracle Primavera Cloud and cannot be modified in P6.
BL Project % Complete Type field
The % complete type of the activity in the project baseline.
BL Project Activity % Complete field
The activity % complete of the activity in the project baseline.
BL Project Cost % Complete field
The cost % complete of the activity in the project baseline.
BL Project Duration % Complete field
The duration % complete of the activity in the project baseline.
BL Project Units % Complete field
The units % complete of the activity in the project baseline.
BL1 % Complete Type field
The % complete type of the activity in the primary baseline.
BL1 Activity % Complete field
The activity % complete of the activity in the primary baseline.
BL1 Cost % Complete field
The cost % complete of the activity in the primary baseline.
BL1 Duration % Complete field
The duration % complete of the activity in the primary baseline.
BL1 Units % Complete field
The units % complete of the activity in the primary baseline.
Cost % Complete field
The percent complete of costs for all labor resources, nonlabor resources, and expenses for the activity.
Calculated as Actual Total Cost divided by At Completion Total Cost multiplied by 100.
Cost % of Planned field
The percent complete of planned costs for all labor resources, nonlabor resources, and expenses for the activity.
Calculated as Actual Total Cost divided by BL Planned Total Cost multiplied by 100. The value can exceed 100. The baseline total cost is the activity's at completion cost from the current baseline.
Duration % Complete field
The duration percent complete for the activity or WBS.
Calculated as Planned Duration minus Remaining Duration divided by Planned Duration multiplied by 100. The value is always between 0 and 100. P6 always calculates Duration % Complete from the Planned Duration and Remaining Duration, even if you enter Duration % Complete manually. For example, if an activity has an Planned Duration of 25.57h and you enter 90% for Duration % Complete P6 will calculate the Remaining Duration as 2.55h and will correct the Duration % Complete to 90.03%.
Duration % of Planned field
The actual duration percent of planned duration for the activity.
The baseline duration is the activity's at completion duration from the project baseline.
Calculated as Actual Duration divided by BL Duration multiplied by 100. The value can exceed 100.
Expense Cost % Complete field
The percent complete of cost for all expenses associated with the activity or WBS.
Calculated as Actual Expense Cost divided by At Completion Expense Cost multiplied by 100. Always in the range 0 to 100.
Labor Cost % Complete field
The percent complete of costs for all labor resources assigned to the activity or WBS.
Calculated as Actual Labor Cost divided by At Completion Labor Cost multiplied by 100. Always in the range 0 to 100.
Labor Units % Complete field
The percent complete of units for all labor resources for the activity or WBS.
Calculated as Actual Labor Units divided by At Completion Labor Units multiplied by 100. Always in the range 0 to 100.
Material Cost % Complete field
The percent complete of costs for all material resources assigned to the activity or WBS.
Calculated as Actual Material Cost divided by At Complete Material Cost multiplied by 100. Always in the range 0 to 100.
Nonlabor Cost % Complete field
The percent complete of costs for all nonlabor resources assigned to the activity or WBS.
Calculated as Actual Nonlabor Cost divided by At Completion Nonlabor Cost multiplied by 100. Always in the range 0 to 100.
Nonlabor Units % Complete field
The percent complete of units for all nonlabor resources for the activity, WBS, or project.
Calculated as Actual Nonlabor Units divided by At Completion Nonlabor Units multiplied by 100. Always in the range 0 to 100.
Percent Complete Type list
Determines the way in which the application calculates the percent complete for the activity.
This default activity percent complete type will be applied to all new activities added to a project. If you change this setting for an existing project that has activities, the percent complete type of those existing activities will not be changed.
Performance % Complete field
The percentage of the activity planned work that is currently complete.
Performance % Complete is used to calculate earned value. It can be based on the activity percent complete, on the 0/100 rule, on the 50/50 rule, depending on the technique for computing earned-value percent complete for the activity's WBS.
Physical % Complete field
The activity percent complete, which is either user-entered or calculated from activity steps.
To calculate Physical % Complete from activity steps, the Calculate Activity % Complete from activity steps option must be enabled for the project.
Schedule % Complete field
The activity schedule percent complete, which specifies how much of the activity's project baseline duration is complete so far.
Calculated based on where the current data date falls relative to the activity's project baseline start and finish dates.
If the data date is earlier than the baseline start, the schedule percent complete is 0. If the data date is later than the baseline finish, the schedule percent complete is 100. The schedule percent complete indicates how much of the activity duration should currently be complete, relative to the selected project baseline.
Scope % Complete field
The percent complete for the activity if the percent complete type is set to scope. Scope is calculated in Oracle Primavera Cloud when P6 is integrated with Oracle Primavera Cloud for scope management.
Units % Complete field
The percent complete of units for all labor and nonlabor resources assigned to the activity.
The percent complete is always in the range 0 to 100.
Calculated as Actual Units divided by At Completion Units multiplied by 100.
Last Published Thursday, October 3, 2024