Configuring Project Calculations
Configure project calculations to define how the application will compute values concerning activities, earned value, and units and costs.
To configure project calculations:
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page:
- Select a project.
- Click Row Actions and select Set Project Preferences.
- In the Project Preferences dialog box, click Calculations.
- On the Calculations page:
- In the Resource Assignments section, specify how the units and costs on assignments and activities should be updated when actual units or costs fields are changed.
- Select whether to Recalculate actual units and costs when Duration % Complete changes.
- Select whether to Link actual to date and actual this period units and costs.
- Click Apply.
Related Topics
Configuring Project Preferences
Configuring History Settings for Analytics
Configuring Project Summarization and Publication Services
Configuring P6 Team Member Status Update Reviews
Configuring P6 Team Member View Preferences
Configuring Project Preferences for Multiple Projects
Last Published Thursday, October 3, 2024