Linking P6 and Primavera Unifier Projects and Activity Sheets.
When the P6 and Primavera Unifier applications are linked, you can link projects in P6 to Primavera Unifier projects and activity sheets. This will allow you to send P6 data to Primavera Unifier.
Notes:
- You cannot link a template project to Primavera Unifier.
- The first time you exchange data between P6 Professional and Primavera Unifier using activity sheet integration, you must initiate the exchange from Primavera Unifier. After the first time, you can initiate the data exchange from P6, P6 Professional, or Primavera Unifier.
To link a P6 to a Primavera Unifier project and activity sheet:
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page:
- Select a project.
- Click Row Actions and select Set Project Preferences.
- In the Project Preferences dialog box, click Integrations.
- On the Integrations page, click Gateway.
- On the Gateway page, select a deployment from the Deployment list.
- Click OK.
Tip:
You need the Allow Integration with Primavera Unifier privilege to change any of the settings on the Integration page of Project Preferences.
Related Topics
Working With Primavera Unifier
Linking P6 and Primavera Unifier Applications Using Schedule Sheets
Linking P6 and Primavera Unifier Projects and Schedule Sheets.
Linking P6 and Primavera Unifier Applications Using Summary Sheets
Linking P6 and Primavera Unifier Projects and Summmary Sheets.
Linking P6 and Primavera Unifier Applications Using Activity Sheets
Filtering Data to be Sent to Primavera Unifier
Exchanging P6 data with Primavera Unifier
Last Published Thursday, June 20, 2024