Future Period Planning: Troubleshooting

Symptom: Future periods are uneditable.

When a future period is not eligible for editing, the spreadsheet cell is gray.

Spreadsheet cells are uneditable when any of the following is true:

Symptom: Inability to enter differing values for Planned Units and Remaining Units.

For assignments on activities that have not started, if the Link planned and at completion for not started activities option is selected on the Calculations tab of the Project Preferences, the total values of the Planned Units and Remaining Early Units for the assignment will always be equal. If this setting is not marked, you can enter different values for the same future period in the Planned Units and Remaining Early Units fields; in this case, the total values for each field are calculated independently for the assignment.

For activities that are in progress, you can always enter different future period values in the Planned Units and Remaining Early Units fields.

Symptom: Future period values have changed since they were entered.

There are many reasons why the future period values you entered for an assignment might change to different values or be placed in a different time period. For example, remaining unit data for an assignment might change when you apply actuals, or if you change the timescale in your view.

Changes to some project, activity or assignment data can cause future period values to be respread and, in some cases, recalculated. When you enter data in future periods, the values are stored in the database. When you modify activity or assignment information which causes the values to respread across future periods, the values stored in the database do not change; only the spread of those values across future periods changes. When you modify activity or assignment data which causes the values to be recalculated, the values you originally entered are recalculated according to the distribution and stored in the database; the original values are lost. If you change the financial period calendar assigned to a project, activity or assignment data might be recalculated.

Changing values in the following fields at the assignment level might respread future period values:

Changing values in the following fields at the activity level might respread future period values:

Performing the following actions might respread future period values:

Changing values in the following fields affecting Assignments might recalculate future period values:

Changing values in the following fields affecting Activities might recalculate future period values:

Related Topics



Last Published Thursday, October 3, 2024